InterContinental Hotel Perth

The building was completely redesigned to accommodate new front-of-house and back-of-house facilities. The hotel now features 240 guest rooms (including pent house suite), and three international restaurant.

Builder

Built.

Value

Undisclosed

CDH Scope Of Works

Supply of Fire Rated Doors (Prolined)

Supply of Non Rated Doors

Supply of door hardware

Supply of fire rated & non rated door frames

Installation of fire rated doors

Installation of non rated doors

Timeline

Start : October 2016

Completion : June 2017

Notes:

The doors were delivered to site prefitted (prolined) with hinges, drop seals and profiled to the frame. This eliminated machining of doors on site which also reduced mess and installation time. First Project using the Proliner System. Manufactured and Installed all timber joinery requirements relating to our scope of works.